Confidential (Paper Mill)
>$500K
777
0
2025




In the winter of 2025, Notch was awarded this project, marked the first phase of a multiphase upgrade to increase the overall capacity of a critical paper machine. Our scope involved the removal of an undersized steam separator, a key component in the paper drying process, and installation of a larger, high-efficiency unit. The work required two months of intensive preplanning for: measuring critical dimensions, setting rigging hardware, and installing fire blankets for fire protection. All field execution was performed within a 24-hour scheduled outage window, ensuring the paper mill’s production cycle remained on track. The successful completion of this phase not only improved the machine’s immediate performance but paved the way for additional upgrades planned over the next year, ensuring long-term gains in production capacity.
With decades of paper mill shutdown expertise and deep knowledge of cascade-type steam systems, our team was ready to meet the challenge head-on.
To ensure success, our team maximized off-site preparation and engineering:
✅ Field-marking all steam and condensate piping cuts in advance,
✅ Developing piping isometrics for prefabrication of new piping spools,
✅ Completing all spool fabrication prior to the outage,
✅ Engineering rigging load points and designing custom rigging assemblies,
✅ Coordinating with the steam vessel manufacturer to pre-position inlet and outlet nozzles, creating a near plug-and-play installation, and
✅ Deploying labor resources experienced in off-shift work, fully prepared for continuous 24-hour operations.
During The 24-Hour Outage:
Metric | Outcome |
| Outage Duration | Completed within the planned 24-hour window |
| System Improvement | Increased steam capacity, improving machine efficiency |
| Project Milestone | Cleared the path for future machine upgrades |
| Client Benefit | Enhanced production performance and long-term scalability |