Confidential Power Plant

Steam Pressure Relief Valve Replacements Confidential (Power Plant) Northeastern U.S. Contract Value: >$250K Total Man Hours: 136 Recordable Injuries: 0 Completion Date: 2023 Project Overview In the summer of 2023, Notch was awarded this project, which involved replacing two welded-in-place steam pressure-relief valves with new flanged pressure-relief valves, while maintaining the exact orientation of the […]

Confidential Paper Mill

Steam Separator Upgrade Confidential (Paper Mill) Northeastern U.S. Contract Value: >$500K Total Man Hours: 777 Recordable Injuries: 0 Completion Date: 2025 Project Overview In the winter of 2025, Notch was awarded this project, marked the first phase of a multiphase upgrade to increase the overall capacity of a critical paper machine. Our scope involved the […]